    Notice Required

    Yes

    Notice Type

    Notice of Intent to File Lien

    Statute

    NDCC § 35-27-15

    Deadline

    10 days before filing lien

    Delivery Method

    Certified mail

    Key Fact: North Dakota

    North Dakota requires a 10-day pre-filing notice before a mechanics lien can be recorded. No project-start preliminary notice is required.

    Understanding North Dakota Requirements

    North Dakota does not require a preliminary notice at the start of a project. Instead, under NDCC § 35-27-15, claimants must send a Notice of Intent to File Lien 10 days before filing lien to preserve their right to record a mechanics lien.

    While North Dakota does not mandate a project-start notice, the pre-filing notice requirement is still a critical step. Failing to send the Notice of Intent to File Lien within the required timeframe will prevent you from recording a valid mechanics lien.

    LienFlash is expanding to cover North Dakota's pre-filing notice requirements. Our platform will automate the notice generation and delivery process, ensuring you never miss the 10 days before filing lien window.

    LienFlash is Coming to North Dakota

    Join the waitlist to be notified when we launch automated preliminary notice filing in North Dakota.

    Already working in a state we support?