Quick Facts
Notice Required
Yes
Notice Type
Notice of Intent to File Lien
Statute
Mo. Rev. Stat. § 429.010
Deadline
10 days before filing lien
Delivery Method
Certified mail
Key Fact: Missouri
Missouri does not require a project-start preliminary notice. A 10-day notice of intent must be sent before a mechanics lien can be filed.
Understanding Missouri Requirements
Missouri does not require a preliminary notice at the start of a project. Instead, under Mo. Rev. Stat. § 429.010, claimants must send a Notice of Intent to File Lien 10 days before filing lien to preserve their right to record a mechanics lien.
While Missouri does not mandate a project-start notice, the pre-filing notice requirement is still a critical step. Failing to send the Notice of Intent to File Lien within the required timeframe will prevent you from recording a valid mechanics lien.
LienFlash is expanding to cover Missouri's pre-filing notice requirements. Our platform will automate the notice generation and delivery process, ensuring you never miss the 10 days before filing lien window.
LienFlash is Coming to Missouri
Join the waitlist to be notified when we launch automated preliminary notice filing in Missouri.